telefono email reloj flecha-derecha-circulo flecha-abajo-circulo cerrar flecha-derecha vimeo-circulo youtube-circulo flecha-abajo mas-circulo flecha-izquierda google-plus-circulo linkedin-circulo exito hucha-cerdo caja-cerrada camion avion barco medalla usuarios-grupo tablet ojo llave enfocar conexion2 globo-terraqueo lapiz-regla mapa conexion menu-hamburguesa mosaico camara-mas

Boiler Modules S.Korea – Germany

Handling and transport of 10 boiler’s modules weighting up to 195 tons per unit, from port of Gunsan, South Korea, up to Power Plant at Berlin, Germany.

Operations included handling and loading of the 10 pieces in Gunsan Port by a floating crane, ocean transportation up to Hamburg Port. Afterwards transshipment operations in Hamburg on to 5 barges at time and by  inland waterways up to Steglitz quay, a nearby terrain on the canal, unloading of the 5 barges by crawler cranes straight onto 16 axles SPMT modular units for the final road transportation through Berlin City up to Power Plant site.